This is a very brief summary of the history of Avington oil field and how the Hampshire County Council influences whether such projects are approved. It is part of a campaign against oil drilling in the South Downs, South Downs for Nature.
Timeline
Here’s a brief history of the Avington oil field:
- Initial consent (03/02907/HCM) for a single well was given in 2003.
- Oil extraction ceased in 2017 (by which point there were 3 wells).
- Their licence expired in 2018.
- In March 2019, the SDNPA said that Star Energy must submit a timetable for plugging and abandonment of the well and a restoration scheme in line with the conditions on the previous licence.
- In March 2020, Star Energy submitted an application to resume extraction (SDNP/20/01255/CM) from their most profitable well.
- In July 2020, the SDNPA refused the application.
- In 2021 Star Energy appealed the application (SDNP/22/04569/DCOND).
- In December 2021 the planning inspectorate gave Star Energy permission to drill.
How this relates to HCC
Although the Planning Inspectorate deals with appeals (such as the one following the SDNPA’s decision), they make their decision using the local Minerals and Waste Plan, decided on by the HCC, so removing oil and gas from the HMWP is critical to stopping oil extraction within Hampshire.
- The current Hampshire Minerals and Waste Plan (HMWP) is from 2013.
- There is currently a partial update draft, a version of which will be adopted in Spring 2026.
- At some point before then it will become an emerging plan and have some weight.
- Star Energy will have to renew their licence in December 2026 and presumably move to production.
As you can see, currently we expect the new HMWP to be adopted before Avington moves to production. The plan would also affect other oil extraction licenses within Hampshire and so we would hope it would reflect our increased knowledge of the risks of the Climate Crisis and the carbon budget in particular by not allowing any new oil or gas extraction within Hampshire.
It’s worth noting that different parts of the planning application and permission indicate different times when or whether Star Energy will have to renew their licence. It’s unclear what will actually happen.