There are many things to take into account when choosing which installers you invite to tender for a photovoltaic solar and battery installation for your community building, and which one of those to actually carry out the installation.
It is WinACC policy to not recommend or refer you to particular companies. The aim of this advice is to help you understand the appropriate number of installers to ask to tender and to inform your process for then appointing one.
First steps
Does this have to be done a particular way?
If your organisation’s constitution or standing orders require a particular process or minimum number of quotations, make sure you follow that. It may still be possible to use some or all of the information below.
How many companies should I invite to tender?
Many companies will be interested in quoting for your work. One organisation that we worked with received 24 quotes – but too much information and too many options can become confusing. We suggest you approach no more than five or six companies. Allowing for one or two not replying you should then receive four or five submissions. This should be enough to get a clear sense of the likely range of costs and the range/types of system available.
What area should I search within?
The 24 quotes mentioned above came from companies as far away as Stockport and Cirencester, and only eight were from within Hampshire. Installers may be willing to travel a long distance for a large valuable job but there are a number of reasons this might not be a good idea for you.
- Pre-tender site visit. If they’re based a long way away, they may decide not to visit before quoting. But if they don’t, how well will they understand your building and its needs?
- Cost. If your building is more than one to one and a half hours’ drive from their base, extra costs of travel or accommodation may push up their quote.
- Sub-contracting. Some companies achieve national coverage by sub-contracting some or all of their work to others closer to the site. This could create issues around the quality of work if the sub-contractor has had to bid a low price to get the work, and responsibility for dealing with problems during and after installation.
- Aftercare and maintenance. Hopefully problems won’t arise once the system is in use. If they do, someone based closer to your building should be able to respond more quickly, and if your chosen installer provides a maintenance contract then the charges may also be lower.
- Carbon emissions. Your photovoltaic solar system will reduce the carbon emissions your building is responsible for, but a contractor travelling a long distance will generate a lot more emissions during the installation and for after-care, undoing some of your good work.
For all these reasons we suggest you invite companies to tender who are based within one to perhaps one and a half hours’ driving time of your building. This will still give you a wide range of companies to choose from. If you’re not sure how far this is, the Travel Time tool on the desktop version of Google Maps is a quick way to check.
How do I find companies that operate in my area?
There are many ways to find companies and decide which to choose. Some are essential, some are a good idea, some should be treated with caution. Use a combination of the sources below to come up with a long-list of ten to fifteen companies.
Essential
- Whichever company you use, they must be registered with the Microgeneration Certification Scheme (MCS). To some extent this ensures a minimum quality of work, but is also essential if you want to receive payment for any electricity you export to the grid.
- The best way to find MCS registered installers within the area you want to choose from is to use the Find an installer search tool on the MCS website
- Search using the first half of your postcode or a few local towns as the location, and set a radius for the search; you may need several different searches to find all the installers in the area.
- You can also use this tool to check whether a company you’ve found using another method is also MCS registered. It’s worth doing this even if they say they are, as MCS registration may expire, or it may not be true
- Be aware: MCS registration isn’t necessarily a guarantee of high quality; some poor quality work is done by MCS registered firms.
Good ideas
- Recommendations from people you know or who manage other community buildings are worth following up, especially if their solar system was installed a few years ago and there has been time for problems (if any) to appear and be resolved. If possible, go to see their system so you get an idea of what the equipment looks like and the quality of work. We are compiling a list of community buildings that we’ve worked with, who have had solar installed and who will recommend and give references for the company they used.
- Web searches (e.g. “solar panel installers near xxx”) are obviously a good potential source of names, but remember that those at the top of the search list may pay to be there, or their website is designed to achieve that. Some very good companies get most of the business they need through personal recommendations and word of mouth, so may not need to do those things.
Treat with caution
- Adverts and posts on social media. These may be paid-for, and many offer attractive-looking prices, but are often “subject to survey” meaning the price may well change. Others use a click-bait approach and are simply ways to obtain your contact details which are then passed on to many companies you may have no interest in dealing with. Both of these are more of an issue for domestic customers but are still worth being aware of.
- Recommendations from social media. Replies to a request for recommendations in a local Facebook or Whatsapp group can often be from people recommending their own business or ones which family or friends work for.
How do I decide which of the companies to ask to tender?
Filter your long-list of ten to fifteen down to five or six by looking at the following (in no particular order).
Length of time in the industry
- A company that’s been installing solar systems for five to ten years should know what they’re doing, will have weathered previous changes in the marke, and are more likely to be around in another five to ten years in case you need them again, though this may not be easy to confirm. A phrase like “xx years’ experience” on a company website may simply mean the combined experience of certain staff. You can check details at Companies House but the age of a company may not be the same amount of time that they have been installing solar e.g. a general electrical company 15 years old could have moved into the solar sector two years ago.
- Be more cautious if a company is under two to three years old: a lot of new businesses were set up to take advantage of the boom in demand when energy prices rose steeply in 2022. Some may not have firm foundations and others were only intended to last a short time, charging low prices to win a lot of work before folding and giving you nowhere to go if a problem arises – think of double-glazing in the 1990’s.
Relevant experience
- Look for companies who have installed solar systems of the size and type you need. A company may have been around for 10 years and completed 500 installations, but if they were all small to medium domestic jobs, and you’re looking for a commercial-type system with 50 panels and 20kWh of batteries on a 3-phase supply, they may not be right for you.
- Similarly, if you have a particular type of roof, e.g. sheet metal with standing seams, or fibreglass, or curved, then look for companies who have done it or something similar before. Case studies or galleries of previous installations on their website are a good guide. If there aren’t any you should consider why that might be.
Who are they?
- Most companies have an About Us page on their website, but what does it tell you about them? Staff pictures and short biographies can tell you a lot more than generic or corporate information.
Blogs and social media
- If a company is doing a good job, they often like to talk about it and show examples, in news items or blog posts on their website and on social media. Whether a company is talking about a particular installation or something else that their staff are doing outside their normal daily business, or their only presence on social media is paid adverts, it can tell you something about them.
Quality Badges
- May be a good guide, but not all are alike. Some are paid for, and involve little checking by the organisation issuing them. Others may involve a lot more checks, but these may be more about financial and governance status, and less about the quality of installation. Some installers are members of assured networks and have to pass due diligence checks to join, and others may be e.g. “Xxxxxxx Gold/ Platinum” installers, which should indicate a certain level of training and expertise with that manufacturer’s products.
Reviews and ratings
There are a number of places that people can leave reviews and score a company out of five or ten, but some may be better than others.
- Google often has large numbers of reviews which is helpful, but there can be false reviews, including from people within the business, which can affect average scores if there are fewer reviews.
- Checkatrade often relates to smaller businesses, and it used to be possible to select which clients leave a review.
- Trusted Trader also relates to smaller businesses.
- Trustpilot seems to cover larger businesses and claims to prevent dishonest reviews.
The last step – how do I decide which contractor to appoint?
By spending some time coming up with the shortlist that you invited to tender, you’ve hopefully now got three to six good quality tender submissions. Now you have to decide between them. This is where your tender document proves its worth: assess each tender submission against the seven criteria listed in the “Evaluation” section and one other factor.
- Inclusions list. Has it been completed in full, or is anything important missing? If there are really obvious or important omissions e.g. around warranties, health & safety or references, you may want to exclude them straight away on this basis as it may reflect the quality and care they take in other aspects of their work.
- Match to system specification. Is the number and location of panels feasible and what you expected? Is the battery roughly the right size? It probably won’t be exactly what you’d suggested because different makes of panel and batteries come in different sizes.
- Annual yield/ generation. This should relate to the size of the solar system and installers are all meant to use the same basis for calculating this. So the same size system on the same parts of the roof should generate very similar amounts of energy, with variation being down to the efficiency of the panels and inverter. The other factor which can cause variation is if your roof is shaded, in which case there may be different estimates of how much this reduces output. The information supplied should include a calculation including the shade factor; if there’s no shading it will be 1.0, and reduces as the amount of shade increases. If an installer doesn’t include the shade factor or it’s 1.0 when the roof is clearly shaded to some extent, then their figures may be over-estimates.
- Expected bill savings. Check that this has been calculated using your electricity tariff (which you should include in the tender document). If it hasn’t, then make adjustments or take this into account in making your decision.
- Export income. Again, check which export tariff has been used in this calculation. If export income makes up a large proportion of the savings and that tariff isn’t available to you in practice, it could make a significant difference to payback period and lifetime savings.
- Capital purchase price. If several submissions have passed all the other checks, your decision may simply come down to price. So check the maths in the quote and if necessary query anything which isn’t clear. As a guide, based on the quotes received for community buildings advised by us which had a solar and battery system installed during phase 1 (2024/5) of the Community Solar Support Scheme, the average price for solar panels was £938/kW, and for battery storage £511/kWh. As an example, for a system with 10kW of panels and a 10kWh battery the average quoted price was (10 x £938 = £9380) + (10 x £511 = £5110) = £14,491. Quotes may vary by up to 15% either side of the average, and it’s likely that the prices accepted were lower than this figure. Also, estimates received for larger systems in December 2025 were significantly lower at around £850/kW, though due to economies of scale, prices for larger systems are generally lower than average per kW, and above average for smaller systems, particularly below 4kW.
- Payback period and lifetime savings. These measures are derived from annual savings and price, so if they’re important to you they can be a useful way to measure how the two combine. They’ll often be derived from a lifetime cashflow diagram or graph. Be aware that different installers might use different assumptions about future changes in energy tariffs, which will affect these measures. They also depend on the installation cost, so will vary from case to case. These measures should be used as a guide but not as a deciding factor.
- The site visit. Strictly speaking, this isn’t one of the evaluation criteria. But if you have advised the installer to make one to check details on site, you should take it into account. Firstly, did they make a site visit, and if not, why not? Who came? Preferably, it should have been someone with technical knowledge. What questions did they ask, could they answer any questions you had? And what overall feeling did you get from them – were they trustworthy, competent, interested to know about your concerns, e.g. maintaining public access and safety during the works? If two or more companies are very close in all other respects, this could be a deciding factor.