For several years, Winchester City Council has been considering the best way to regenerate the area around Winchester railway station, “Station Approach”.
The next stage is the Concept Masterplan. The draft Concept Masterplan was discussed, and approved, at Winchester City Council Cabinet meeting on 18 June 2025. The meeting is on YouTube, so you can watch it here. It was the first item.
WinACC’s response to the Cabinet report
Phil Gagg, the Chair of our Transport and Plannng Action Group, spoke at the Cabinet meeting to stress the need to future-proof the site, saying:
“… this development is a unique opportunity to provide a transport interchange at the railway station. It is vital that we don’t miss this once-in-a-generation opportunity.
“We must make sure we have enough space in this development to allow good connections between all district buses and between buses and trains. With a good interchange at the station, good fast public transport journeys could be offered between all main points in the district and all points on the railway system. For example:
- New Alresford to Southampton,
- Bishop’s Waltham to Farnborough,
- Otterbourne to Reading.
“All bus services could be reconfigured to serve both the station and the centre. This would encourage a switch to public transport and a reduction in transport emissions in the district.
“An interchange for a district the size of Winchester requires at least seven bus bays to enable good connections. The plan we see here does not provide anywhere near the space necessary.
“WinACC asks the Cabinet to make it clear that they don’t want to lose this opportunity by accident. Instead, decide that you want transport experts to scope how much space is needed for an interchange before deciding on what goes where.
If this plan goes ahead, we will lose forever the possibility of integrating public transport in the district.”
Cabinet discussion
In the discussion about the Master Plan and our reaction, the leader of the City Council, Martin Tod, emphasised that he had said from the start that the plan must improve transport. The creation of the new Mayoral Combined Authority that will become the transport authority, and of unitary Councils will make developments like this easier to manage.
The City Council emphasised that they had had lots of discussions with bus companies who control bus timetables, with the teams looking at the bus implications of North Park-and-Ride, the Central Winchester Regeneration team, and the current transport authority, Hampshire County Council. Design Engine said that all these agreed that they were happy with the two current bus stops, with in future a double bus stop on Station Hill, plus the addition of a bus lane on Andover Road.
Councillor Kelsie Learney said that they’d never intended to have a new bus station at the station. Directing buses through the station causes delays – it is more important to get buses moving more quickly and reliably into the town centre, where more passengers [currently] want to go.
She also said that the Master Plan will deliver the 7 bus stops we suggested would be needed, if you add up the bus stops in Andover Road, Stockbridge Road and City Road that all serve the station, as well as the bus stops already at the station and two new ones suggested in the Master Plan.
Martin Tod said it was a good example of positive placemaking, co-created with local people. This Master Plan must be seen as part of their overall suite of planning policies including those in the Local Plan and Local Transport Plan 4.
WinACC hopes
After the meeting, Phil Gagg said, “I agree with Councillor Tod that this is the best plan for Station Approach so far. But we need more thinking about how this development can help create a really good public transport system for Winchester district. In particular, how do we:
- make it simple for people to find the right bus when they’ve just arrived in Winchester
- provide enough space for buses that connect with trains
- create a route for buses to move quickly between the station and the town centre
- get most buses to stop at both the station and the town centre
- set timetables that offer short waiting times for people who transfer between bus and train
- plan good walking and cycling routes to and in the station area”.
Background: where has this “Concept Master Plan” come from?
In 2024, Winchester City Council appointed local architects Design Engine to develop a “Concept Masterplan” that will guide the development of the Station Approach area.
They say, “Using the agreed development principles, we aim to create a viable, local and community driven concept masterplan…l Environmental, economic, and social wellbeing all lie at the heart of what we want to create. This is an opportunity to explore transforming a key gateway to Winchester and protecting what makes the city special. With your help we’re keen to deliver a scheme based on the four Development Principles already consulted on:
- A connected, sustainable development,
- High quality design, positive placemaking,
- Development for Winchester’s future,
- Co-creating with residents, businesses and stakeholders.”
The team carried out a baseline survey, workshops with local residents and businesses, and a six-week consultation in late 2024, supported by an online webinar and a drop-in information event, to get feedback on draft proposals under six key themes.
Read the Council’s web pages on the Station Approach project
Curious about how thinking has been changing? See Winchester City Council news release from 2017 here, and WinACC’s comments over the last 10 years can be accessed using the tag Station Approach.